Basic Assignments
 
Options & Settings
 
Main Time Information
Color Code: Green
Created By: Shannon Scoffield
Created Date/Time: 5/16/2016 3:14 pm
 
Action Status: Blank (new)
Show On The Web: Yes - (public)
 
Time Id: 3846
Template/Type: Daily Tasks
Title/Caption: Daily Tasks
Start Date: 5/29/2015
Main Status: Active

click to enlarge - photo by: Shannon Scoffield -
click to enlarge - photo by: Shannon Scoffield -
 


Notes:
• Finished up the payroll changes and calculating commissions based off of either profits or gross sales. Also added an option to save the commission reports as pdf documents.
• Uploaded files and tested.
• Went into Logan to work with my guys. I talked quite a bit with the project manager about the adilas service hub model and other options. It just keeps growing in size and options. That is kind of fun.
• I worked with a developer on his project for stock/units and saving report settings.
• Three developers were working on icon menus.
• The project manager talked about projects. We went through them, defined them, and then started to assign them.
• A developer, the project manager, and I had a conference call with a client. We talked about GPS/RFID tag tracking. We are building some GPS and logistic tracking pieces to help him out. Great phone call. Lots of options.
• Signed off on code for Steve.
• Started into some code sign-offs for a developer and his GPS/RFID tag tracking stuff for elements of time.
• Emails and tech support.
• Spent the last hour or so talking with project managers about how to open up and build out the adilas service hub model. We also talked about development grants, training interns, and helping people excel at what they are good at. Fun stuff. 30 miles.